FUB4 Building on the University Campus

DESCRIPTION

Construction of a building and its urbanization for the Fundació Universitària del Bages, known by the acronym FUB4. The building is aimed to cover the needs of space expansion in response to the teaching program enlargement. The completion of the project and the building works in 9 months allowed the Foundation to start operating the investment on time. The building consists of a first floor and two upper floors. The ground floor houses the CIFE (Center for Innovation and Training in Education) and a kindergarten. On the second floor, the LAB for children between 0 and 12 years laboratories. The second floor is for university training with 6 classrooms of different formats and sizes with an open study area.

Download PDF profile

BUILDING STATUS

Project: September 2020 - March 2022
Construction: 9 months
Production: 5 months

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.